PROJECTS & DEMOLITIONS
With the capability to manage entire demolition projects from start to finish,
we handle everything from plant and equipment removals to large-scale demolitions.
Our services include site establishment, access management, demolition execution, material transportation, waste removal, site restoration, as well as comprehensive health & safety, quality management, scheduling, and contract administration.
PROJECT
EXXON MOBIL
The Macaulay project team have completed the demolition of numerous bulk storage tanks around New Zealand. In 2017 Macaulay was contracted to Exxon Mobil to demolish a large redundant fuel storage tank at the Seaview Terminal in Wellington. The tank was 27m in diameter and 15m tall. After extensive consultation with the client a suitable methodology based on the horizontal tear method was developed. The project was completed on time and as per the methodology.
Location: Seaview, Wellington
Duration: 2 weeks
Metal recovered: 200 tonnes
Completed: November 2014
PROJECT
FPSO Umuroa /
TUI OIL FIELD
In May 2021 the Macaulay project team took delivery of close to 3,000 tonnes of heavy anchor chain, sea anchors and wire ropes from the failed Tui Oil Field. The chain was discharged directly onto Port Taranaki from a heavy ocean-going supply vessel. In only a week the Macaulay team cut the chain
up into manageable sections and removed it to a separate stock piling area
on the port.
One month later it was loaded direct from the port onto a bulk vessel and shipped to a steel mill in South Korea. Macaulay’s team facilitate all aspects
of such projects including organising the sale and shipping of the processed material.
Location: Port Taranaki, New Plymouth
Duration: 2 months
Metal removed: 3,000 tonnes
Completed: May - June 2021
PROJECT
Solid Energy
Coal Mine
Solid Energy contracted Macaulay to demolish a significant amount of above ground coal mining assets at the Huntly East and West Mines in Huntly. The project also included filling a 100 metre deep ventilation shaft with 10,000 tonnes of fill and a 300 tonne concrete capping slab.
Location: Huntly, Waikato
Duration: 12 Months
Metal recovered: 2,000 tonnes
Completed: October 2017
PROJECT
CENTREPORT
WELLINGTON
After dismantling Centre Ports B and C container cranes in 2005, Macaulay was contracted to dismantle and remove the Paceco D container crane.
The crane weighing just over 700 tonnes was dismantled and lowered to
the ground in large sections. At ground level it was cut down into smaller pieces for efficient removal from site. An extension of the project was the dismantling and removal of 6 container handling straddle carriers. The Macaulay team exceeded expectations, and the project was completed on time with significant financial returns for Centre Port.
Location: Centre Port, Wellington
Duration: 4 weeks
Metal recovered: 960 tonnes
Completed: March 2011
PROJECT
NEW PLYMOUTH
POWER STATION

TRANSFORMERS
Macaulay are New Zealand’s leading expert at dismantling redundant electrical transformers. We have completed an extensive number of significant transformer removal projects across New Zealand. A significant transformer project was completed in 2013. Port Taranaki purchased the
New Plymouth Power Station from Contact Energy.
Macaulay Metals purchased 5 surplus generating transformers weighing
120 tonnes each. The Transformers were broken down onsite and the steel components were loaded into containers and exported direct from site and the copper cores were sent to Macaulay’s Wellington Yard for further processing.
Location: New Plymouth
Duration: 2 months
Metal recovered: 600 tonnes
Completed: December 2013
PROJECT
NEW PLYMOUTH
POWER STATION
Electrix subcontracted Macaulay for a major decommissioning project at the former New Plymouth Power Station. Decommissioned in 2008 and partially demolished in 2015, the site retained its generator hall, administration annex, main stack, and fully enclosed substations, which remained connected to the national grid until 2019.
We were tasked with removing all substation components, leaving the buildings empty for the new owners, Port Taranaki. The work included confined space operations, underground cable removal, dismantling suspended switchyards 17 metres high, and disposing of nine transformers, four of which exceeded 100 tonnes.
Location: New Plymouth, Taranaki
Duration: 7 Months
Metal recovered: 500 tonnes
Completed: August 2020
Transform what’s RECOVERABLE with us
Whether you’re interested in selling or buying metal or need help with a project or demolition, we’re ready to hear from you.
GET IN TOUCH
Wellington
45 Seaview Rd,
Lower Hutt

04 589 2222
Opening hours

Monday to Friday:
7:30am – 4:30pm

Saturday: 

8:00am – Midday
TAURANGA
25 Glenlyon Ave,
Tauranga

07 975 1340
Yard opening soon
ROTORUA
73 Old Taupo Rd,
Rotorua

07 348 6966
Opening hours

Monday to Friday:
8:00am – 4:30pm

Saturday: 

8:00am – Midday
PALMERSTON NORTH
49 Malden St,
Palmerston North

06 357 7071
Opening hours

Monday to Friday:
8:00am – 4:30pm

Saturday: 

8:00am – Midday
WHAKATANE
147A Commerce St,
Whakatane
07 308 9100
Opening hours

Monday to Friday:
7:30am – 4:30pm
Saturday: 

8:00am – Midday

0800 Scrap yard | 0800 72 72 79